Cabling: almost always transfers
Cable in the wall belongs to the building. Cat5e and Cat6 runs that test clean carry a new camera or reader exactly as well as the old one. We test every run during the survey and keep what passes; a takeover proposal should show reused runs as a savings line. The exceptions are runs that are too long for PoE, damaged, or undocumented and untraceable.
Cameras and recorders: transfer if they are open
IP cameras that speak the ONVIF standard can usually be adopted by a new recorder or platform. Cameras locked to one manufacturer's ecosystem, or analog cameras on coax, may work only with their original recorder. Recorders themselves transfer when we can log in; a recorder whose administrator password left with the previous company may be recoverable by reset, or may be a brick. Ask for admin credentials in writing before the old contract ends.
Access control panels: the most common lock-in
Door controllers run on manufacturer software, and some manufacturers sell only through certified dealers. If the new integrator is certified on your platform, the panel transfers and nothing changes at the doors. If not, the choice is to find a certified dealer or replace the controller while keeping readers, locks and cabling. Readers and door hardware transfer far more often than the panel behind them.
Credentials: cards, fobs and phones
Proprietary card formats can be read only by that manufacturer's readers. Open formats and mobile credentials move more easily. On a takeover we test a sample card on the proposed reader before anything is ordered, so that a re-badging exercise is a line on the proposal rather than a surprise.
Alarm panels and monitoring accounts
The intrusion panel almost always stays; it is the communicator and the monitoring account that change. The communicator may be locked to the previous dealer's central station and need replacing. The monitoring contract has its own term and notice period, separate from the installation relationship. Read it before you give notice on the integrator.
Software licenses and cloud subscriptions
Licenses are usually tied to the end customer, not the dealer, and transfer with a reseller change request to the manufacturer. Some are tied to the dealer's account and must be re-purchased. The previous integrator is obliged to tell you which; the manufacturer will confirm it directly if asked.
Documentation: rarely transfers, always needed
As-built drawings, cable labels, IP address schedules, port maps and programming notes are the things that make a system serviceable. If the previous company never produced them, the first job of the new integrator is to create them, and that labor belongs on the proposal honestly rather than hidden in the first service call.
The takeover checklist
- Collect administrator credentials for every recorder, panel and software platform while the old contract is still live.
- Get the monitoring contract and note its term and notice period.
- Ask the manufacturer which licenses are customer-owned and which are dealer-owned.
- Have the new integrator test cabling, adopt cameras and test a credential before quoting.
- Insist on a proposal that lists what stays, what changes and why, line by line.
- Budget for documentation if none exists.
Takeover questions
Can you take over a system if we don't have the passwords?
Usually. Most recorders and panels can be reset to factory and reprogrammed, which costs labor but not hardware. A few platforms cannot be recovered without the original dealer; we identify those during the survey.
Will our existing cards still work?
If the readers stay, yes. If the controller changes and the card format is proprietary, re-badging may be needed. We test a sample card on the proposed reader before anything is ordered.
Do we have to replace the alarm panel?
Rarely. The panel usually stays; the communicator and monitoring account are what change when you move to a new central station.